How to Shut Down an AI Project That Isn't Working

An AI project is rarely shut down because it fails on a given day. It stays alive because it always seems a quarter away from working, and nobody wrote down at approval what it had to show and by when.

Carlos Andrés Ramírez ·

An AI project is rarely shut down because it fails on a given day. It stays alive because it always seems a quarter away from working, and nobody wrote down at approval what it had to show and by when.

Picture an assistant for the customer service team that was approved eight months ago. The first weeks brought a good demo, then a data fix, then a second version. Every month the team brings a real improvement and a reasonable case for waiting one more month. Nobody has decided the project should continue: nobody has simply decided it should end, and the budget renews itself with the calendar.

The idea behind this article is that shutting down an AI project is a management decision and not a technical verdict, and that it is only made well if the exit criterion was written the day the project was approved. You need to tell apart three situations that look alike from the outside and call for opposite actions, and put someone with a name in charge of deciding.

The short answer

How do you decide to shut down an AI project that isn't working?

You compare what the project has shown against the exit criterion set at approval, on the review date set at that time. If the project falls short, the business owner chooses between three paths: fix what is failing, narrow the scope or close it. If that criterion never existed, the first job is to write it today, with today's information, and set a short review date. Without a criterion and a date, a project is not shut down: it wears out.

First support

An AI project is shut down by the rule written beforehand, not the one improvised afterwards

When a project is approved, enthusiasm is at its highest and information at its lowest. When it has to be shut down, it is the other way round: there is plenty of information and everyone is invested in the work done. That is why the exit criterion is written at the start, however uncomfortable, with three elements: which number has to move, by how much and by what date.

Take a returns operation: "by 31 March, half of all requests are resolved without human intervention and average response time falls from two days to one." With that sentence, the March review is a reading. Without it, it is a negotiation, and in a negotiation the most recent argument wins, which is almost always "it's nearly there". The criterion does not have to be perfect. It has to exist before the results are seen, because a criterion adjusted after the score is known measures nothing.

Second support

"Not working" can mean three different things, and each calls for the opposite decision

Most conversations about cancelling a project lump different situations under the words "it doesn't work". Separating them is what stops you closing something that could be fixed and keeping something that cannot.

  • It does not work technically: the agent makes mistakes at a rate the operation cannot tolerate, and after several rounds of tuning the error barely falls. The usual answer here is to close it or narrow the scope to the cases where it does get things right.
  • It works, but nobody uses it: the agent handles the cases well, but the team works around it because it does not fit how they work or because nobody redesigned the process around it. The technology is not what gets switched off here: either adoption is fixed or the project closes for lack of an owner.
  • It works and it is used, but the number does not move: minutes are saved that never turn into lower costs or more capacity sold. The problem here is the business case, and fixing it usually means deciding what happens with the time that was freed.

The reason to separate the three is the cost of misdiagnosis. If an adoption problem is treated as a technical one, another half year goes into improving a model that was already good enough. If a technical problem is treated as an adoption one, training is organised to convince a team to use something it rightly does not trust.

An AI project nobody dares to switch off is not being prudent, it is paying for the right not to decide.

BECOME

Third support

Shutting a project down well leaves something standing, and one person decides it

There are two reasons closing gets postponed. The first is that nobody has the authority to do it: the technical team does not want to declare failure, the business sponsor depends on it, and the steering committee sees it every three months among other priorities. The decision needs an owner: whoever answers for the business result the project promised, not whoever built it.

The second reason is that closing looks like losing everything. It does not, if it is done with method. Before switching off, you note what was learned, which data is now in order, which part of the work serves another case and which people on the team move to which project. A closure with that list costs one meeting. A zombie project costs, every month, the team, the infrastructure and the attention of whoever runs the area.

The framework

Three questions order the decision, and the first two are answered with data the project already has

1. What does the exit criterion say?
The result is compared with the number, threshold and date fixed at approval. It is read by the business owner, not the project team. If it does not exist, it is written today and a review is set for six to eight weeks out.
2. Which of the three diagnoses is it?
Technical, adoption or business case. It is answered with the error rate by kind of case, the team's actual usage and the effect on the area's P&L. Each diagnosis leads to a different decision.
3. What is kept, and who decides?
One person signs off on continuing, narrowing or closing, and writes down what is reused: data, lessons, people. Without this question, closing looks like losing everything, which is why it gets postponed.

Take the AI project that has been running longest without a clear result and ask its business sponsor to write, in three lines, which number it should have moved, by how much and by when. If they cannot write it, that is the first finding. If they can and the number has not moved, the decision already has a date.

Frequently asked questions

When should you cancel an AI project?

When, on the agreed review date, the result is below the exit criterion and the diagnosis shows the problem cannot be fixed by a reasonable change of scope, adoption or business case. The decision belongs to the owner of the business result, not the technical team, and it helps to write down what gets reused.

How do you know if an AI pilot is failing?

You check it against three things: the number it was meant to move and the committed date, the error rate by kind of case, and actual usage by the team. A pilot can fail in different ways. It can make too many mistakes, it can work and go unused, or it can be used without changing any result. Each calls for a different decision, which is why it pays to separate them.

Who decides to close an AI project in a company?

Whoever answers for the business result the project promised, usually the head of the area or business unit. The technical team reports what the system has shown, but should not be the one to decide, because it is too close to the work done. It should be one person with a name, not a committee.

What if an AI project has no exit criterion?

Write one now. The business owner sets which number should move, by how much and by what date, using the information that already exists, and schedules a short review six to eight weeks out. A late criterion is worse than an initial one, but better than none, and it stops the project from renewing itself out of habit.

Let's review the exit criterion for your oldest AI project

From the idea to the operation

Adoption is not communicated: it is designed with the teams who will operate the capability, and measured against a baseline.